As stated by NVIDIA and SB Energy ·
"8 IT-GW of AI factory capacity" resulting from at least 10 GW of new generation; OpenAI to be the customer.
NVIDIA and SB Energy (press release, 8-K Ex. 99.1) sourcePiketon · Pike County, Ohio · United States
SB Energy is developing an AI data center campus on the former Portsmouth Gaseous Diffusion Plant site in Pike County, Ohio, leased to an OpenAI affiliate for NVIDIA AI factories. NVIDIA and SB Energy state 8 IT-GW of planned capacity, with an initial 4.25 IT-GW. SB Energy's Nov. 19, 2026 IPO filing lists construction as not started, with phases expected to reach service between 2028 and 2032.
As stated by NVIDIA and SB Energy ·
"8 IT-GW of AI factory capacity" resulting from at least 10 GW of new generation; OpenAI to be the customer.
NVIDIA and SB Energy (press release, 8-K Ex. 99.1) sourceAs stated by NVIDIA ·
Initial deployment: leases for approximately 4.25 GW of IT load covered by NVIDIA's residual value guaranties; NVIDIA may secure about 3.8 GW more at its discretion.
NVIDIA (Form 8-K) sourceAs stated by NVIDIA and SB Energy ·
"At least 10 GW of new energy generation" to be built by SB Energy and SoftBank; DOE cites 9.2 GW of natural gas within 10 GW.
NVIDIA and SB Energy (press release, 8-K Ex. 99.1) sourceAs stated by American Electric Power ·
"Proposed 10.4 GW data center campus"; IT/facility basis not stated. The initial 800 MW of load is to be served with existing transmission capacity.
American Electric Power (Form 10-Q) sourceAn OpenAI affiliate is the tenant for approximately 4.25 GW of IT load; the release names OpenAI as customer for 8 IT-GW.
Exclusive AI compute infrastructure provider (DSX AI factory platform); also provides lease credit support.
AEP Ohio Transmission Company to build three 765 kV lines for the campus.
SB Energy's Nov. 19 IPO registration amendment says the PORTS-Pike campus is not yet under construction and expects first-phase service in 2028 and final completion in 2032.
Source published 19 Nov 2026 · Catalog recorded 23 Nov 2026 · Agent review
SoftBank Group's Q2 FY2026 materials say $5.6 billion of advance payments for power generation equipment is to be recouped from the PORTS-Pike power generation project, describe the campus as preparing for construction and say its $3.7 billion equipment loss is unrelated to PORTS-Pike.
Source published 10 Nov 2026 · Catalog recorded 16 Nov 2026 · Agent review
SB Energy's project site says clearing and grading for the first 800 MW phase will begin in the coming weeks, after surveys, geotechnical work and permitting; it does not report construction as started.
Source published 20 Oct 2026 · Catalog recorded 31 Oct 2026 · Agent review
SB Energy is developing an AI data center campus on the former Portsmouth Gaseous Diffusion Plant site in Pike County, Ohio, leased to an OpenAI affiliate for NVIDIA AI factories. NVIDIA and SB Energy state 8 IT-GW of planned capacity, with an initial 4.25 IT-GW. SB Energy's Nov. 19, 2026 IPO filing lists construction as not started, with phases expected to reach service between 2028 and 2032.
Source published 17 Aug 2026 · Catalog recorded 30 Oct 2026 · Agent review
DOE announced the partnership with SoftBank/SB Energy and AEP Ohio for a 10 GW data center development at the Portsmouth Site.