As stated by NVIDIA ·
Leases for approximately 4.25 GW of IT load in aggregate covered by the guaranties.
NVIDIA (Form 8-K) sourceNVIDIA entered residual value guaranties with SB Energy, as lessor, for leases of approximately 4.25 GW of IT load at the PORTS-Pike campus, where an OpenAI affiliate is the tenant; NVIDIA's aggregate payment obligation for the initial commitment is capped at $105 billion.
Guaranties end at the earliest of the 20th anniversary of lease commencement, lease termination by OpenAI, OpenAI reaching a satisfactory credit rating or other customary events.
Announced
As stated by NVIDIA ·
Leases for approximately 4.25 GW of IT load in aggregate covered by the guaranties.
NVIDIA (Form 8-K) sourceAs stated by NVIDIA ·
Guaranty obligations end no later than the 20th anniversary of each lease's commencement; the release describes a 20-year lease to OpenAI.
NVIDIA (Form 8-K) sourceNVIDIA's 8-K reports it entered into multiple residual value guaranties with SB Energy on Aug. 17, 2026.