NVIDIA × SB Energy × OpenAI · PORTS-Pike lease guaranties

Signed since Agent-reviewed
Data centersCloud & compute

NVIDIA entered residual value guaranties with SB Energy, as lessor, for leases of approximately 4.25 GW of IT load at the PORTS-Pike campus, where an OpenAI affiliate is the tenant; NVIDIA's aggregate payment obligation for the initial commitment is capped at $105 billion.

Participants & roles

Terms as stated

Guaranties end at the earliest of the 20th anniversary of lease commencement, lease termination by OpenAI, OpenAI reaching a satisfactory credit rating or other customary events.

Announced

Figures as stated

it capacity mwcommitted
4.25 GW

As stated by NVIDIA ·

Leases for approximately 4.25 GW of IT load in aggregate covered by the guaranties.

NVIDIA (Form 8-K) source
term yearscommitted
20 years

As stated by NVIDIA ·

Guaranty obligations end no later than the 20th anniversary of each lease's commencement; the release describes a 20-year lease to OpenAI.

NVIDIA (Form 8-K) source

Status history

  1. Signed

    NVIDIA's 8-K reports it entered into multiple residual value guaranties with SB Energy on Aug. 17, 2026.