SoftBank ties $5.6B of power-equipment advance payments to PORTS-Pike generation SoftBank Group's Q2 FY2026 materials say $5.6 billion of advance payments for power generation equipment is to be recouped from the PORTS-Pike power generation project, describe the campus as preparing for construction and say its $3.7 billion equipment loss is unrelated to PORTS-Pike.
§ + Catalog entry · Agent review 28 Oct 2026
AEP Ohio × SB Energy · Piketon transmission SB Energy committed to pay for new 765 kV transmission that AEP Ohio is to build for the PORTS-Pike data center campus. AEP's Q3 2026 10-Q says definitive agreements with the campus customer, executed in August 2026, set a budget of about $5 billion for three 765 kV lines.
+ Catalog entry · Agent review 17 Aug 2026
NVIDIA × SB Energy × OpenAI · PORTS-Pike lease guaranties NVIDIA entered residual value guaranties with SB Energy, as lessor, for leases of approximately 4.25 GW of IT load at the PORTS-Pike campus, where an OpenAI affiliate is the tenant; NVIDIA's aggregate payment obligation for the initial commitment is capped at $105 billion.
+ Catalog entry · Agent review 17 Aug 2026
PORTS-Pike Technology Campus SB Energy is developing an AI data center campus on the former Portsmouth Gaseous Diffusion Plant site in Pike County, Ohio, leased to an OpenAI affiliate for NVIDIA AI factories. NVIDIA and SB Energy state 8 IT-GW of planned capacity, with an initial 4.25 IT-GW. SB Energy's Nov. 19, 2026 IPO filing lists construction as not started, with phases expected to reach service between 2028 and 2032.