As stated by Riot Platforms ·
Critical IT capacity under the lease, delivered as powered pads in three phases.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceCorsicana · Texas · United States
Riot Platforms leases land, powered pads and related infrastructure at its Corsicana, Texas facility to Anthropic for 15 years, covering 910 MW of critical IT capacity. Riot targets three phases: 400 MW from June to September 2027, 200 MW from December 2027 to January 2028 and 310 MW on July 30, 2028.
As stated by Riot Platforms ·
Critical IT capacity under the lease, delivered as powered pads in three phases.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceAs stated by Riot Platforms ·
'1.0 GW of utility load' for the site.
Riot Platforms (SEC Form 8-K, Exhibit 99.2) sourceAs stated by Riot Platforms ·
$6 million per IT MW overall; $2 million funded by Riot and $4 million reimbursed to the tenant in phases.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceAs stated by Riot Platforms ·
Approximate initial 15-year contract value with Anthropic; excludes extension options.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceAs stated by Riot Platforms ·
Initial lease term; two five-year extension options.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceDelivers the land, power infrastructure and powered pads and owns the high- and medium-voltage infrastructure.
Anthropic PBC, named as the 'Frontier AI Lab' in Riot's 10-Q; the release and deck do not name it.
Riot's quarterly report identifies Anthropic PBC as the Frontier AI Lab at Corsicana and sets a first-block target of June 28, 2027; no construction start is stated.
Source published 04 Nov 2026 · Catalog recorded 07 Nov 2026 · Agent review
Riot Platforms leases land, powered pads and related infrastructure at its Corsicana, Texas facility to Anthropic for 15 years, covering 910 MW of critical IT capacity. Riot targets three phases: 400 MW from June to September 2027, 200 MW from December 2027 to January 2028 and 310 MW on July 30, 2028.
Source published 04 Nov 2026 · Catalog recorded 06 Nov 2026 · Agent review
Riot reports a signed 910 MW lease at Corsicana with planned phased delivery from September 2027.