As stated by Riot Platforms ·
Critical IT load capacity the premises are expected to provide: 400, 200 and 310 MW phases.
Riot Platforms (SEC Form 10-Q) sourceRiot Corsicana, LLC signed a triple-net powered land lease with Anthropic PBC on Oct. 28, 2026, effective Nov. 4, for 910 MW of critical IT capacity in three phases. Base rent is $130 per kW of critical IT capacity per month, escalating 3% a year.
15 years from the first block to the 15th anniversary of Phase 3 commencement, with two five-year extension options.
Announced
As stated by Riot Platforms ·
Critical IT load capacity the premises are expected to provide: 400, 200 and 310 MW phases.
Riot Platforms (SEC Form 10-Q) sourceAs stated by Riot Platforms ·
Approximate initial 15-year contract value; excludes extension options.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceAs stated by Riot Platforms ·
Runs to the 15th anniversary of Phase 3 commencement; two five-year extension options.
Riot Platforms (SEC Form 10-Q) sourceRiot's 10-Q says Riot Corsicana entered the lease with Anthropic PBC on Oct. 28, 2026; it became effective Nov. 4, 2026.