Micron's fiscal 2026 annual report says construction of its first Boise memory fab began in October 2023 and projects first DRAM wafer output in mid-calendar 2027.
Source published 09 Oct 2026 · Catalog recorded 21 Nov 2026 · Agent review
Boise · Idaho · United States
Micron broke ground on its first Boise, Idaho memory fab in September 2022; its FY2026 10-K says construction began in October 2023, with first DRAM wafer output projected in mid-calendar 2027.
No figure is recorded with sufficient source support.
Micron's fiscal 2026 annual report says construction of its first Boise memory fab began in October 2023 and projects first DRAM wafer output in mid-calendar 2027.
Source published 09 Oct 2026 · Catalog recorded 21 Nov 2026 · Agent review
Micron broke ground on its first Boise, Idaho memory fab in September 2022; its FY2026 10-K says construction began in October 2023, with first DRAM wafer output projected in mid-calendar 2027.
Source published 09 Jul 2026 · Catalog recorded 09 Oct 2026 · Agent review
Micron's FY2026 10-K says construction of the Boise fab began in October 2023; the filing gives the month only, stored as the first of the month. The earlier entry was dated to a July 2026 progress release.