TeraWulf Justified Data Campus

Hawesville · Kentucky · United States

Under construction since Agent-reviewed
Data centers

TeraWulf is building an AI data center campus at the former Century Aluminum Hawesville site in Hancock County, Kentucky, where Anthropic has leased approximately 401 MW of critical IT load under 20-year leases. TeraWulf's November 2026 presentation describes the campus as under construction and targets three buildings for delivery: 137.6 MW in Q4 2027, 137.6 MW in Q1 2028 and 125.6 MW in Q2 2028.

Figures as stated

it capacity mwplanned
401 MW

As stated by TeraWulf ·

Approximately 401 MW of critical IT load leased to Anthropic; the Nov. 2026 presentation targets delivery from Q4 2027 through Q2 2028. Not yet built.

TeraWulf source
facility capacity mwcommitted
482 MW

As stated by TeraWulf ·

Up to 482 MW of electric service under the PSC-approved retail electric service agreement with Big Rivers and Kenergy; a ceiling, not delivered power or IT load.

TeraWulf source

Participants & roles

  • TeraWulfdeveloper

    Landlord through its subsidiary Raylan Data LLC; acquired the site on Feb. 2, 2026.

    Source
  • Anthropictenant

    Tenant of approximately 401 MW of critical IT load under a 20-year lease.

    Source
  • Big Rivers Electric Corporationutility

    Authorized by the Kentucky PSC to implement the retail electric service agreement.

    Source
  • Kenergy Corp.utility

    Authorized by the Kentucky PSC to implement the retail electric service agreement.

    Source
  • Fluorbuilder

    Fluor Enterprises, Inc., under a definitive EPC agreement on a GMP basis covering engineering, procurement, construction, testing and commissioning for three buildings.

    Source

Catalog timeline

Catalog entry
TeraWulf's Hawesville, Kentucky campus leased to Anthropic for about 401 MW

TeraWulf is building an AI data center campus at the former Century Aluminum Hawesville site in Hancock County, Kentucky, where Anthropic has leased approximately 401 MW of critical IT load under 20-year leases. TeraWulf's November 2026 presentation describes the campus as under construction and targets three buildings for delivery: 137.6 MW in Q4 2027, 137.6 MW in Q1 2028 and 125.6 MW in Q2 2028.

Source published 06 Jul 2026 · Catalog recorded 25 Oct 2026 · Agent review

Stage history

  1. Under construction from Announced

    TeraWulf's Q3 2026 presentation labels Justified 'UNDER CONSTRUCTION' and says 'Construction underway (campus-wide)'; the start date is not stated.

  2. Announced

    TeraWulf announced a 20-year Anthropic lease for a purpose-built AI campus to be developed in multiple phases at the Hawesville site; no construction start is stated.

    TeraWulf ↗Agent review