As stated by SpaceX ·
First cluster: 'approximately 210 megawatts of compute power'; IT versus facility basis not stated.
SpaceX (Form 424B4 prospectus) sourceMemphis · Tennessee · United States
SpaceX's COLOSSUS II comprises AI training data centers on Tulane Road in Memphis, Tennessee, and on Stateline Road in Southaven, Mississippi. SpaceX's June 2026 prospectus says it brought online a first cluster of about 110,000 GB200 processors (about 210 MW of compute power) and a second cluster of 110,000 GB300 processors (220 MW), and expects a next phase to add at least 220,000 GB300 processors and over 400 MW. SpaceX says the site can run entirely on its self-built behind-the-meter natural gas plant, alongside Megapack batteries.
As stated by SpaceX ·
First cluster: 'approximately 210 megawatts of compute power'; IT versus facility basis not stated.
SpaceX (Form 424B4 prospectus) sourceAs stated by SpaceX ·
First cluster: 'approximately 110,000 GB200 processors'.
SpaceX (Form 424B4 prospectus) sourceAs stated by SpaceX ·
Second cluster: '220 megawatts of compute power', brought online in 64 days; basis not stated.
SpaceX (Form 424B4 prospectus) sourceAs stated by SpaceX ·
Second cluster: '110,000 GB300 processors'.
SpaceX (Form 424B4 prospectus) sourceAs stated by SpaceX ·
Next phase: 'over 400 additional megawatts of compute power' expected once fully operational; a lower bound, not summed with the delivered clusters.
SpaceX (Form 424B4 prospectus) sourceAs stated by SpaceX ·
Next phase: 'at least 220,000 additional GB300 processors'.
SpaceX (Form 424B4 prospectus) sourceThe plaintiff's counsel and local press report that a federal court in Mississippi denied xAI's motion to dismiss on Oct. 30, 2026; a preliminary-injunction ruling is still pending.
Source published 30 Oct 2026 · Catalog recorded 04 Nov 2026 · Agent review
SpaceX's COLOSSUS II comprises AI training data centers on Tulane Road in Memphis, Tennessee, and on Stateline Road in Southaven, Mississippi. SpaceX's June 2026 prospectus says it brought online a first cluster of about 110,000 GB200 processors (about 210 MW of compute power) and a second cluster of 110,000 GB300 processors (220 MW), and expects a next phase to add at least 220,000 GB300 processors and over 400 MW. SpaceX says the site can run entirely on its self-built behind-the-meter natural gas plant, alongside Megapack batteries.
Source published 12 Jun 2026 · Catalog recorded 03 Nov 2026 · Agent review
SpaceX's prospectus states the first and second COLOSSUS II clusters were brought online and a further phase is expected; partial operation.