Two Korean outlets reported in mid-November 2026 that site preparation and utility work for Y2 had begun, while full construction remains planned for July 2027 and the first cleanroom for June 2029.
Source published 16 Nov 2026 · Catalog recorded 24 Nov 2026 · Agent review