As stated by SK hynix ·
Company-stated approximate USD equivalent of first-fab construction investment; equipment installation excluded.
SK hynix sourceYongin · Gyeonggi · South Korea
SK hynix confirms first-fab construction at Yongin, targeting its first cleanroom opening in February 2027. Its 3Q26 results release says Yongin Phase 1 enters full-scale operation next year (2027). Reports from a November 2026 press tour say SK hynix put Y1 construction at about 89% complete.
As stated by SK hynix ·
Company-stated approximate USD equivalent of first-fab construction investment; equipment installation excluded.
SK hynix sourceKorean press reports from a November 2026 site tour say SK hynix put Y1 construction at about 89% complete and still targets its first cleanroom opening in February 2027, three months earlier than planned.
Source published 16 Nov 2026 · Catalog recorded 16 Nov 2026 · Agent review
In its October 28 third-quarter results, SK hynix said Yongin Phase 1 is set to enter full-scale operation next year, while keeping the scale and timing of investment flexible.
Source published 28 Oct 2026 · Catalog recorded 02 Nov 2026 · Agent review
SK hynix confirms first-fab construction at Yongin, targeting its first cleanroom opening in February 2027. Its 3Q26 results release says Yongin Phase 1 enters full-scale operation next year (2027). Reports from a November 2026 press tour say SK hynix put Y1 construction at about 89% complete.
Source published 07 Aug 2026 · Catalog recorded 09 Oct 2026 · Agent review
SK hynix confirms first-fab construction at Yongin, targeting its first cleanroom opening in February 2027.