As stated by Prologis representatives (as reported by Journal-News) ·
'the proposed 250-megawatt data center'; IT or facility basis not stated. Repeated by WYSO (July 9, 2026) and Journal-News (Nov. 12, 2026).
Journal-News sourceTrenton · Ohio · United States
Prologis is developing 'Project Mila', a four-building data center campus at 3000 Arnold Brown Industrial Drive in the Trenton Industrial Park, Butler County, Ohio, on land bought from the city. Local press reports a 250 MW plan attributed to Prologis representatives. Trenton's planning commission approved the site plan on March 30, 2026, and Prologis says construction has begun. On Nov. 12, 2026 Trenton Data Center Campus LLC sued the city in federal court, arguing that the Issue 17 charter amendment passed on Nov. 3 cannot apply to the previously approved project.
As stated by Prologis representatives (as reported by Journal-News) ·
'the proposed 250-megawatt data center'; IT or facility basis not stated. Repeated by WYSO (July 9, 2026) and Journal-News (Nov. 12, 2026).
Journal-News sourcePrologis is developing 'Project Mila', a four-building data center campus at 3000 Arnold Brown Industrial Drive in the Trenton Industrial Park, Butler County, Ohio, on land bought from the city. Local press reports a 250 MW plan attributed to Prologis representatives. Trenton's planning commission approved the site plan on March 30, 2026, and Prologis says construction has begun. On Nov. 12, 2026 Trenton Data Center Campus LLC sued the city in federal court, arguing that the Issue 17 charter amendment passed on Nov. 3 cannot apply to the previously approved project.
Source published 12 Nov 2026 · Catalog recorded 13 Nov 2026 · Agent review
Prologis states 'the company has begun construction' and that construction activities have begun (Journal-News, Nov. 12, 2026); WCPO (Nov. 4, 2026) also reports the project 'already under construction'. The date is the statement's date, not a recorded construction start; opponents describe the work as site work.
Trenton's planning commission voted that Prologis's site plan complies with the zoning code (WCPO; Journal-News Apr. 1 corroborates); the city packet lists the Prologis site plan review on the Mar. 30, 2026 agenda.