NEXTDC S4 Horsley Park

Sydney · New South Wales · Australia

Under construction since Agent-reviewed
Data centers

NEXTDC's S4 Sydney campus at Horsley Park has development approval and is under construction: NEXTDC's FY26 results (Aug. 27, 2026) report construction on track with the first slab on ground and total planned power upgraded to 365 MW, with 250 MW in progress. After its capital expenditure review, NEXTDC said on Nov. 20, 2026 that S4 remains a priority: 250 MW of the 365 MW planned IT load is contracted and the first 115 MW phase is under construction, with billing expected from 1H FY28.

Figures as stated

Power · basis unspecifiedplanned
350 MW

As stated by NEXTDC ·

Approximate total planned power stated in May 2026; 250 MW initial tranche is a subset. NEXTDC upgraded the total to 365 MW on Aug. 27, 2026.

NEXTDC source
Power · basis unspecifiedplanned
365 MW

As stated by NEXTDC ·

S4 Sydney upgraded to 365 MW: 250 MW in progress, remaining 115 MW in plan; basis not stated.

NEXTDC (ASX announcement) source
it capacity mwplanned
365 MW

As stated by NEXTDC ·

'At S4 Sydney, 250MW of the 365MW planned IT load is contracted, with the first phase (115MW) under construction.' The AGM presentation lists Phase 2 (135 MW) in the NSW planning process and the remaining 115 MW in planning, not yet contracted. Planned, not delivered.

NEXTDC (ASX release) source

Participants & roles

Catalog timeline

Catalog entry
NEXTDC S4 Horsley Park added to the catalog

NEXTDC's S4 Sydney campus at Horsley Park has development approval and is under construction: NEXTDC's FY26 results (Aug. 27, 2026) report construction on track with the first slab on ground and total planned power upgraded to 365 MW, with 250 MW in progress. After its capital expenditure review, NEXTDC said on Nov. 20, 2026 that S4 remains a priority: 250 MW of the 365 MW planned IT load is contracted and the first 115 MW phase is under construction, with billing expected from 1H FY28.

Source published 08 May 2026 · Catalog recorded 09 Oct 2026 · Agent review

Stage history

  1. Under construction from Permitted

    NEXTDC reports S4 construction on track with the first slab on ground; press reported Multiplex starting construction at the end of March 2026.

  2. Permitted

    NEXTDC reports development approval for its S4 Sydney campus and an initial development tranche in progress.

    NEXTDC ↗Agent review