As stated by Caverion ·
Caverion describes 'a new 70-megawatt building' served by a 70 MW substation; DCD and W.Media earlier reported up to 70 MW from a Nebius LinkedIn post. Basis (IT or facility) not stated.
Caverion sourceMäntsälä · Finland
Nebius is building a second data center in Mäntsälä, Finland, next to its first facility there. Nebius's Q3 2026 shareholder letter expects the site to deploy capacity in 2027. Contractor Caverion describes a new 70 MW building and says the substation serving it will be completed in autumn 2027.
As stated by Caverion ·
Caverion describes 'a new 70-megawatt building' served by a 70 MW substation; DCD and W.Media earlier reported up to 70 MW from a Nebius LinkedIn post. Basis (IT or facility) not stated.
Caverion sourceCaverion Finland says it will design and deliver a 70 MW substation, worth about EUR 15 million, for Nebius's new 70 MW Mäntsälä building, with completion in autumn 2027.
Source published 02 Oct 2026 · Catalog recorded 23 Nov 2026 · Agent review
Nebius is building a second data center in Mäntsälä, Finland, next to its first facility there. Nebius's Q3 2026 shareholder letter expects the site to deploy capacity in 2027. Contractor Caverion describes a new 70 MW building and says the substation serving it will be completed in autumn 2027.
Source published 12 Nov 2026 · Catalog recorded 22 Nov 2026 · Agent review
Nebius announced on Aug. 13, 2026 that it is building a second data center in Mäntsälä (reported by DCD and W.Media); its Nov. 12 shareholder letter expects the site to deploy capacity in 2027.