Microsoft plans a data center campus at 0 Huffaker Road in Floyd County, Georgia, near Rome. A Development of Regional Impact application submitted on Oct. 20, 2026 names the project ATL80 and describes three buildings of up to 1,659,000 square feet on 349.03 acres, an estimated peak connected load of 422 MW from Georgia Power and overall completion in 2032. Microsoft announced the site in October 2023.

Figures as stated

capex usdreported
$1B

As stated by Microsoft, per All On Georgia ·

More than $1 billion stated in October 2023; press report, not updated by the 2026 filing.

All On Georgia source

Participants & roles

Catalog timeline

Catalog entry
Microsoft ATL80 campus added: state filing lists 422 MW peak load and 2032 completion in Floyd County

Microsoft plans a data center campus at 0 Huffaker Road in Floyd County, Georgia, near Rome. A Development of Regional Impact application submitted on Oct. 20, 2026 names the project ATL80 and describes three buildings of up to 1,659,000 square feet on 349.03 acres, an estimated peak connected load of 422 MW from Georgia Power and overall completion in 2032. Microsoft announced the site in October 2023.

Source published 20 Oct 2026 · Catalog recorded 05 Nov 2026 · Agent review

Stage history

  1. Announced

    Microsoft announced its Huffaker Road data center campus and land purchase; the 2026 regional review filing is not a permission.

    All On Georgia ↗Agent review