Data centersCloud & compute

NSW granted State Significant Development consent (SSD-58601963) on Oct. 1, 2026 for Microsoft's data centre at 6 Honeman Close, Huntingwood, Sydney: a five-storey building with 40 data halls and a 96 MW IT load, with a stated capital investment of A$1,263,226,278.

Figures as stated

Participants & roles

Catalog timeline

Catalog entry
NSW approves Microsoft's 96 MW Huntingwood data centre

NSW granted State Significant Development consent (SSD-58601963) on Oct. 1, 2026 for Microsoft's data centre at 6 Honeman Close, Huntingwood, Sydney: a five-storey building with 40 data halls and a 96 MW IT load, with a stated capital investment of A$1,263,226,278.

Source published 01 Oct 2026 · Catalog recorded 14 Oct 2026 · Agent review

Stage history

  1. Permitted

    NSW grants development consent subject to conditions.