Hyperion · Richland Parish

Richland Parish, Louisiana · United States

Under construction since Agent-reviewed
Data centers

Meta reports ongoing construction of its Richland Parish data center, which will house the Hyperion AI cluster. Turner, DPR and Mortensen lead the build. In July 2026 Meta said it is expanding the site to 5 GW of compute capacity, an investment of more than $50 billion in the region.

Figures as stated

contract value usdcommitted
$875M

As stated by Meta ·

Contracts with Louisiana businesses; lower bound and a subset of project spending.

Meta source
Power · basis unspecifiedplanned
5 GW

As stated by Meta ·

Meta is "expanding" the Richland Parish data center "to 5 GW in compute capacity"; IT or facility basis not stated.

Meta source
capex usdplanned
$50B

As stated by Meta ·

"More than $50 billion in the Richland Parish region" for the expansion; lower bound.

Meta source
contract value usdcommitted
$1.6B

As stated by Meta ·

More than $1.6 billion contracted with local Louisiana businesses to date; lower bound, a later cumulative value than the December 2025 figure, not an addition to it.

Meta source

Participants & roles

Catalog timeline

Source added
Entergy reports a settlement recommending certification of its Evest gas plants, with an LPSC decision expected in December

Entergy's Nov. 2, 2026 10-Q says the application remains pending and the settlement is not a commission order; Entergy names Evest, not Meta, while local reporting links the seven plants to Meta's second Richland Parish site.

Source published 02 Nov 2026 · Catalog recorded 05 Nov 2026 · Agent review

Catalog entry
Hyperion · Richland Parish added to the catalog

Meta reports ongoing construction of its Richland Parish data center, which will house the Hyperion AI cluster. Turner, DPR and Mortensen lead the build. In July 2026 Meta said it is expanding the site to 5 GW of compute capacity, an investment of more than $50 billion in the region.

Source published 19 Dec 2025 · Catalog recorded 09 Oct 2026 · Agent review

Stage history

  1. Under construction

    Meta reports ongoing construction of its Richland Parish data center, which will house the Hyperion AI cluster. Turner, DPR and Mortensen lead the build.

    Meta ↗Agent review