Kazakhstan's government reports construction at Data Center Valley in Ekibastuz, where a first phase of three data centers totalling 304 MW is planned. On Nov. 6, 2026 it said work on the first 68 MW data center had moved to foundations and infrastructure, with commissioning scheduled for Q2 2027, and that pit excavation for the 164 MW Firebird AI data center was 70% complete with launch scheduled for Q3 2027. Firebird says Phase 1 of its Kazakhstan AI Factory is under construction there with Kazakhtelecom.
Figures as stated
Power · basis unspecifiedplanned
300 MW
As stated by Government of Kazakhstan (Prime Minister's press service) ·
Step-down substation infrastructure with a capacity of 300 MW, expandable to 1 GW in the future; plus 15 km of transmission lines.
U.S. export license secured for 45,000 NVIDIA Grace Blackwell GPUs for Phase 1 of Firebird’s Kazakhstan AI Factory; not a delivery or installation figure.
As stated by Government of Kazakhstan (Prime Minister's press service) ·
'The first phase of the project provides for the creation of three data centers with a total capacity of 304 MW' (68 MW, Firebird AI 164 MW and 72 MW, as stated); IT versus facility basis not stated.
As stated by Government of Kazakhstan (Prime Minister's press service) ·
First data center, reported by Kazakhtelecom's chairman; commissioning scheduled for Q2 2027. August's account gave the first facility as 50 MW; the difference is not explained.
Firebird says Phase 1 of its Kazakhstan AI Factory is under construction with Kazakhtelecom at Data Center Valley; no site-operator or ownership role is stated.
The government said on Nov. 6, 2026 that the first 68 MW data center has moved to foundation work with commissioning scheduled for Q2 2027, and a 164 MW Firebird AI data center is due to launch in Q3 2027.
Firebird said on October 23, 2026 that Phase 1 of its Kazakhstan AI Factory is under construction with Kazakhtelecom at Data Center Valley and targets commercial launch in the third quarter of 2027.
The August 13 account places the first 50 MW facility in active construction and targets June 2027 operation; the October 6 update corroborates construction without establishing commissioning.
Kazakhstan's government reports construction at Data Center Valley in Ekibastuz, where a first phase of three data centers totalling 304 MW is planned. On Nov. 6, 2026 it said work on the first 68 MW data center had moved to foundations and infrastructure, with commissioning scheduled for Q2 2027, and that pit excavation for the 164 MW Firebird AI data center was 70% complete with launch scheduled for Q3 2027. Firebird says Phase 1 of its Kazakhstan AI Factory is under construction there with Kazakhtelecom.