Cape Station

Beaver County, Utah · United States

Operational · partial since Agent-reviewed
Power & grid

Fervo’s first Cape Station GeoBlock declared commercial operation on September 30, 2026, as reported in its October 1 release. The first block produced 33 MW net; the remaining Phase I blocks were still commissioning and Phase II remained under construction. On Nov. 18, 2026 Fervo said it executed a 105 MW transmission service agreement with Longroad Energy for firm delivery rights on the Milford Gen Lead line, bringing Cape Station's contracted long-term firm transmission capacity to 505 MW; the new service is expected to begin in 2028, subject to final regulatory approvals. Fervo's Nov. 10, 2026 Form 10-Q says it is renegotiating the delivery timing under certain existing Phase II PPAs, with delivery expected in the early 2030s.

Figures as stated

generation mwdelivered
33 MW

As stated by Fervo Energy ·

First GeoBlock only; not the capacity of the full Cape Station development.

Fervo Energy source

Participants & roles

Catalog timeline

Catalog entry
Cape Station added to the catalog

Fervo’s first Cape Station GeoBlock declared commercial operation on September 30, 2026, as reported in its October 1 release. The first block produced 33 MW net; the remaining Phase I blocks were still commissioning and Phase II remained under construction. On Nov. 18, 2026 Fervo said it executed a 105 MW transmission service agreement with Longroad Energy for firm delivery rights on the Milford Gen Lead line, bringing Cape Station's contracted long-term firm transmission capacity to 505 MW; the new service is expected to begin in 2028, subject to final regulatory approvals. Fervo's Nov. 10, 2026 Form 10-Q says it is renegotiating the delivery timing under certain existing Phase II PPAs, with delivery expected in the early 2030s.

Source published 01 Oct 2026 · Catalog recorded 09 Oct 2026 · Agent review

Stage history

  1. Operational

    Fervo’s October 1, 2026 release states that the first Cape Station GeoBlock declared commercial operation on September 30; the other Phase I blocks remained in commissioning and Phase II under construction.

    Fervo Energy ↗Agent review