As stated by Drax Group ·
Phase 1 target 'up to 100MW' of compute capacity, operational from Q1 2028; IT/facility basis not stated.
Drax Group (RNS 5051B) sourceNorth Yorkshire · United Kingdom
Drax Group signed an agreement with Brookfield and Radiant, Brookfield's UK-headquartered AI infrastructure platform, to jointly develop, deliver and operate an AI data centre on the Drax Power Station estate in North Yorkshire, with capital through the Brookfield-Qai AI infrastructure joint venture. Phase 1 targets up to 100MW, operational from Q1 2028 using grid power; Phase 2 is an ambition for an additional 500MW between 2028 and 2031 powered behind the meter by the station's generation; Phase 3 is an ambition for more capacity after 2031. Brookfield estimates total potential investment, including semiconductor chips, could exceed £20 billion, with an initial £2.5 billion as part of Phase 1.
As stated by Drax Group ·
Phase 1 target 'up to 100MW' of compute capacity, operational from Q1 2028; IT/facility basis not stated.
Drax Group (RNS 5051B) sourceAs stated by Drax Group ·
Phase 2 ambition to develop options for an additional 500MW between 2028 and 2031, behind the meter; subject to consents. Not to be added to Phase 1.
Drax Group (RNS 5051B) sourceJointly develops, delivers and operates the data centre; leads design, customer engagement and commercialisation.
Investment capital and operating capabilities through the Brookfield-Qai AI infrastructure joint venture.
Drax says it will submit a planning application to North Yorkshire Council in the coming months; no application or approval is recorded.
Source published 04 Nov 2026 · Catalog recorded 05 Nov 2026 · Agent review
Drax Group signed an agreement with Brookfield and Radiant, Brookfield's UK-headquartered AI infrastructure platform, to jointly develop, deliver and operate an AI data centre on the Drax Power Station estate in North Yorkshire, with capital through the Brookfield-Qai AI infrastructure joint venture. Phase 1 targets up to 100MW, operational from Q1 2028 using grid power; Phase 2 is an ambition for an additional 500MW between 2028 and 2031 powered behind the meter by the station's generation; Phase 3 is an ambition for more capacity after 2031. Brookfield estimates total potential investment, including semiconductor chips, could exceed £20 billion, with an initial £2.5 billion as part of Phase 1.
Source published 03 Nov 2026 · Catalog recorded 04 Nov 2026 · Agent review
Drax announces the signed agreement with Brookfield and Radiant to develop the phased data centre.