Digital Realty × Rönesans Ankara Temelli data center campus

Ankara · Ankara · Türkiye

Under construction since Agent-reviewed
Data centers

Digital Realty and Rönesans Infrastructure's joint venture is building its first Türkiye data center campus in Temelli, Ankara, designed for more than 22 MW of carrier-neutral IT capacity with completion scheduled for 2028.

Figures as stated

it capacity mwplanned
22 MW

As stated by Digital Realty ·

Designed to support more than 22 MW of carrier-neutral IT capacity; Rönesans also states more than 22 MW of IT capacity for the first phase.

Digital Realty (GlobeNewswire release) source
capex usdplanned
$450M

As stated by Mehmet Fatih Kacır, Türkiye Minister of Industry and Technology ·

Initial stage: basic infrastructure and building construction, as reported by Anadolu Agency.

Anadolu Agency source
capex usdplanned
$900M

As stated by Mehmet Fatih Kacır, Türkiye Minister of Industry and Technology ·

Additional allocation to cooling systems and IT infrastructure, as reported by Anadolu Agency; stated separately, not summed.

Anadolu Agency source
capex usdplanned
$4.1B

As stated by Mehmet Fatih Kacır, Türkiye Minister of Industry and Technology ·

Fixed capital investment once all phases are complete at the Ankara Temelli Başkent Organized Industrial Zone site, as reported by Anadolu Agency and Hürriyet.

Anadolu Agency source

Participants & roles

Catalog timeline

Stage history

  1. Under construction

    Digital Realty states land, power and permitting are secured and early construction work has already commenced.