As stated by Bell Canada ·
Planned Sherwood campus capacity; IT versus facility power basis is not specified, and this is not current energized load.
Government of Saskatchewan / Bell Canada sourceRural Municipality of Sherwood, Saskatchewan · Canada
BCE says all four first-phase buildings at its Saskatchewan AI campus are under construction and continues to expect the first data hall to come online in the first half of 2027.
As stated by Bell Canada ·
Planned Sherwood campus capacity; IT versus facility power basis is not specified, and this is not current energized load.
Government of Saskatchewan / Bell Canada sourceBCE's Q3 report restates the first-hall expectation and reports about C$475 million spent at Sherwood through Sept. 30; the expansion to 1.2 GW remains a non-binding memorandum.
Source published 05 Nov 2026 · Catalog recorded 07 Nov 2026 · Agent review
The October 1 government-hosted update supports ongoing building work and a first-hall target in the first half of 2027, while leaving the 300 MW power basis unspecified.
Source published 01 Oct 2026 · Catalog recorded 25 Oct 2026 · Agent review
BCE says all four first-phase buildings at its Saskatchewan AI campus are under construction and continues to expect the first data hall to come online in the first half of 2027.
Source published 01 Oct 2026 · Catalog recorded 09 Oct 2026 · Agent review
Bell reports rising structural steel and all four first-phase buildings taking shape at its Saskatchewan AI campus.