As stated by Applied Digital ·
'a $3 billion, 280-megawatt (MW) AI Factory near Harwood, North Dakota', 'designed with the ability to scale beyond its initial 280MW'; IT/utility basis not stated.
Applied Digital sourceHarwood · North Dakota · United States
Applied Digital's Polaris Forge 2 AI Factory campus near Harwood, North Dakota, is leased for 200 MW of critical IT load to an unnamed U.S. investment-grade hyperscaler under a lease of about 15 years. Applied Digital said on Nov. 24, 2026 that the first 25 MW data hall of the campus's initial 150 MW building had reached Ready for Service, after base-build commissioning of the building's first 75 MW phase. The rest of the campus remains under construction.
As stated by Applied Digital ·
'a $3 billion, 280-megawatt (MW) AI Factory near Harwood, North Dakota', 'designed with the ability to scale beyond its initial 280MW'; IT/utility basis not stated.
Applied Digital sourceAs stated by Applied Digital ·
The release calls the campus 'a $3 billion ... AI Factory' and does not break the amount down; it is the company's planned figure, not a reported cost.
Applied Digital sourceAs stated by Applied Digital ·
Lease 'covers 200 megawatts (MW) of critical IT load', 'phased within two buildings'; the lessee is an unnamed U.S. investment-grade hyperscaler. Includes the delivered 25 MW.
Applied Digital sourceAs stated by Applied Digital ·
'approximately $5 billion in total contracted revenue over an estimated 15-year lease term'; lease revenue, not capex. The 10-K says the lease has two five-year renewal options, which this amount excludes.
Applied Digital sourceAs stated by Applied Digital ·
'an estimated 15-year lease term'; base term, excluding renewal options.
Applied Digital sourceAs stated by Applied Digital ·
10-Q: 'Our two buildings at our Polaris Forge 2 campus, with an aggregate 300MW of capacity, are currently under construction'; basis not stated. Differs from the 200 MW critical IT lease and the 280 MW announcement.
Applied Digital (Form 10-Q) sourceAs stated by Applied Digital ·
'the integrated fit-out of the first 25 MW data hall' completed and Ready for Service achieved; this is part of the first 75 MW phase of the 'initial 150 MW data center building'. IT/utility basis not stated.
Applied Digital sourceDesigns, develops, owns and operates the campus through subsidiaries APLD FAR-01 and APLD FAR-02 (lessors) under APLD ComputeCo 2 (issuer of the 2031 notes).
Applied Digital's Polaris Forge 2 AI Factory campus near Harwood, North Dakota, is leased for 200 MW of critical IT load to an unnamed U.S. investment-grade hyperscaler under a lease of about 15 years. Applied Digital said on Nov. 24, 2026 that the first 25 MW data hall of the campus's initial 150 MW building had reached Ready for Service, after base-build commissioning of the building's first 75 MW phase. The rest of the campus remains under construction.
Source published 24 Nov 2026 · Catalog recorded 25 Nov 2026 · Agent review
Applied Digital reported the first 25 MW data hall of the initial 150 MW building Ready for Service; partial operation, with the rest of the campus still under construction.
Applied Digital's lease release describes the Polaris Forge 2 campus as 'currently under construction near Harwood, North Dakota'; the 10-K dates the groundbreaking to Aug. 18, 2025, which conflicts with the announcement's planned September 2025 date.
Applied Digital announced it plans to break ground in September 2025 on Polaris Forge 2, a $3 billion, 280 MW AI Factory near Harwood, North Dakota.