Applied Digital is building Delta Forge 1, an AI Factory campus in Rapides Parish, Louisiana, designed for an initial 430 MW of total utility power and up to 300 MW of critical IT load in two 150 MW buildings. It broke ground on Jan. 22, 2026, and the 300 MW is leased under two leases of about 15 years to an unnamed U.S. investment-grade hyperscaler. On Nov. 23, 2026 Applied Digital said it had closed a $300 million delayed-draw bridge facility to fund continued development and construction of the campus.
Figures as stated
Power · basis unspecifiedplanned
430 MW
As stated by Applied Digital ·
'An initial 430 MW of total utility power' across two buildings, enabling up to 300 MW of critical IT load; utility power, not IT load. The company says the campus can 'scale considerably in 2028 and beyond'.
Critical IT load covered by the lease with an unnamed U.S. high investment-grade hyperscaler; the 10-K describes two approximately 15-year leases totaling 300 MW. Not delivered.
State release: 'plans to develop a $3.6 billion ... AI factory campus in Rapides Parish'. Applied Digital's own releases give no campus investment figure.
Applied Digital is building Delta Forge 1, an AI Factory campus in Rapides Parish, Louisiana, designed for an initial 430 MW of total utility power and up to 300 MW of critical IT load in two 150 MW buildings. It broke ground on Jan. 22, 2026, and the 300 MW is leased under two leases of about 15 years to an unnamed U.S. investment-grade hyperscaler. On Nov. 23, 2026 Applied Digital said it had closed a $300 million delayed-draw bridge facility to fund continued development and construction of the campus.