As stated by Amkor Technology ·
"Approximately $2 billion" by full project completion; superseded by later totals.
Amkor Technology (Business Wire release, reproduced by Nasdaq) sourcePeoria · Arizona · United States
Amkor broke ground in October 2025 on its advanced packaging and test campus in Peoria, Arizona, with production of the first phase expected in early 2028; Apple is stated as its first and largest customer. In September 2026 Amkor announced a second phase, raising the planned investment to about $12 billion, with phase 2 construction expected to begin in late 2027 and finish by the end of 2029.
As stated by Amkor Technology ·
"Approximately $2 billion" by full project completion; superseded by later totals.
Amkor Technology (Business Wire release, reproduced by Nasdaq) sourceAs stated by Amkor Technology ·
"A total of $7 billion across two phases"; superseded by the September 2026 total.
Amkor Technology (Business Wire release, reproduced by Nasdaq) sourceAs stated by Amkor Technology ·
Phase 2 expansion "increases the project's planned investment to approximately $12 billion."
Amkor Technology (Business Wire release, reproduced by Finviz) sourceAs stated by Amkor Technology ·
"Over 750,000 square feet of cleanroom space" upon completion of both phases; the 2026 release restates cleanroom in square metres (about 93,000 m²).
Amkor Technology (Business Wire release, reproduced by Nasdaq) sourceAmkor's 10-Q filed October 27, 2026 says construction costs incurred on its Arizona facility reached $553.3 million as of September 30, 2026, and that construction is underway.
Source published 27 Oct 2026 · Catalog recorded 28 Oct 2026 · Agent review
Amkor broke ground in October 2025 on its advanced packaging and test campus in Peoria, Arizona, with production of the first phase expected in early 2028; Apple is stated as its first and largest customer. In September 2026 Amkor announced a second phase, raising the planned investment to about $12 billion, with phase 2 construction expected to begin in late 2027 and finish by the end of 2029.
Source published 08 Sept 2026 · Catalog recorded 27 Oct 2026 · Agent review
Amkor announced the groundbreaking of the campus; its 10-Q confirms construction of the Arizona Facility is underway.
Amkor announced plans to build an advanced packaging and test facility in Peoria, Arizona.