As stated by Xcel Energy ·
New wind capacity provided for under the Clean Energy Accelerator Charge; recorded separately, not summed.
Xcel Energy sourceXcel Energy agreed terms to serve a planned Google data center in Pine Island, Minnesota, with Google funding 1,400 MW of wind, 200 MW of solar and 300 MW of long-duration storage through a Clean Energy Accelerator Charge; the agreement requires Minnesota PUC approval.
Electric service customer; pays all costs of its new service and new grid infrastructure.
Proposed 15-year contract (press reports of the PUC filing); pending MPUC approval.
Announced
As stated by Xcel Energy ·
New wind capacity provided for under the Clean Energy Accelerator Charge; recorded separately, not summed.
Xcel Energy sourceAs stated by Xcel Energy ·
New solar capacity provided for under the Clean Energy Accelerator Charge.
Xcel Energy sourceAs stated by Xcel Energy ·
Long-duration storage: a 300 MW (30 GWh) Form Energy iron-air battery installation.
Xcel Energy sourceXcel announces the Electric Service Agreement will be filed for review and says the MPUC must formally approve it.