As stated by TeraWulf ·
Contracted power capacity at Muskie after the amendment, up from 500 MW; phased delivery, not delivered power.
TeraWulf sourceTeraWulf and Kentucky Power, an American Electric Power company, executed amended and restated transmission infrastructure and energy service agreements that raise contracted power at the Muskie Data Campus from 500 MW to 1 GW.
Contract duration and delivery terms are not recorded.
Announced
As stated by TeraWulf ·
Contracted power capacity at Muskie after the amendment, up from 500 MW; phased delivery, not delivered power.
TeraWulf sourceAmended and restated agreements executed October 1, 2026 increase contracted power capacity from 500 MW to 1 GW.
Transmission infrastructure and energy service agreements were executed concurrently with the Muskie acquisition, which closed effective May 22, 2026.