As stated by Riot Platforms ·
Critical IT load capacity; 96 MW anticipated in December 2027, the remainder in June 2028.
Riot Platforms (SEC Form 10-Q) sourceRiot's 191 MW critical IT lease at Rockdale, announced in August 2026 with an unnamed frontier AI lab, is with Anthropic PBC according to Riot's Q3 10-Q. Riot anticipates 96 MW in December 2027 and the remainder in June 2028, and values the initial 20-year term at about $9.1 billion.
20 years from full deployment anticipated in June 2028, through June 2048 per Riot's August release, with two five-year renewal options at the tenant's election.
Announced
As stated by Riot Platforms ·
Critical IT load capacity; 96 MW anticipated in December 2027, the remainder in June 2028.
Riot Platforms (SEC Form 10-Q) sourceAs stated by Riot Platforms ·
Approximate total initial contract revenue over the 20-year term; excludes extension options.
Riot Platforms (SEC Form 8-K, Exhibit 99.1) sourceAs stated by Riot Platforms ·
Commences on full deployment anticipated in June 2028; two five-year renewal options.
Riot Platforms (SEC Form 10-Q) sourceRiot announced the executed 191 MW Rockdale lease on Aug. 10, 2026; its 10-Q later names the tenant as Anthropic PBC.