As stated by HUMAIN, DataVolt and NEOM ·
Contemplated offtake of up to 50 MW, described as half of the initial 100 MW under construction within the planned 360 MW first phase; IT versus facility basis not stated.
NEOM sourceHUMAIN and DataVolt announced a preliminary framework agreement with Nebius, signed at NVIDIA GTC Berlin, under which Nebius would become an anchor customer for up to 50 MW of the initial 100 MW under construction at the planned Oxagon AI campus in NEOM.
Capacity expected to become operational in phases from Q4 2027; further commercial agreements required.
Announced
As stated by HUMAIN, DataVolt and NEOM ·
Contemplated offtake of up to 50 MW, described as half of the initial 100 MW under construction within the planned 360 MW first phase; IT versus facility basis not stated.
NEOM sourceThe release announces a preliminary framework agreement, not a binding lease.