As stated by Michigan Public Service Commission staff ·
Primary supply agreement duration.
Michigan Public (Planet Detroit) sourceThe Michigan Public Service Commission conditionally approved DTE Electric's special contracts with Google for a planned data center in Van Buren Township, including a 20-year primary supply agreement with an 80% minimum billing demand and Google-funded development of up to 1,600 MW of renewable generation and 480 MW of battery storage by DTE.
Supplier under the special contracts; to develop, own and operate the funded resources.
20-year primary supply agreement; termination payment covers at least 15 years of minimum charges.
Announced
As stated by Michigan Public Service Commission staff ·
Primary supply agreement duration.
Michigan Public (Planet Detroit) sourceAs stated by Michigan Public Service Commission ·
Up to 1,600 MW of renewable energy for DTE to develop, paid by Google; separate from 480 MW of battery storage.
Michigan Public (Planet Detroit) sourceThe MPSC grants conditional approval of the DTE Electric–Google special contracts.
Google announces a clean capacity agreement with DTE while evaluating the Van Buren Township site.