Blackstone Digital Infrastructure Trust × Amazon · Indiana and Mississippi data center joint ventures

Signed since Agent-reviewed
Data centersCloud & compute

Blackstone Digital Infrastructure Trust agreed on Nov. 11, 2026 to acquire a 75.1% controlling interest in two joint ventures with Amazon affiliates that will own two AWS data center campuses, valued at $5.0 billion in aggregate. The 13 newly constructed data centers, nine in northern Indiana and four in Mississippi, have 647 MW of aggregate IT power capacity and will be 100% leased back to Amazon Data Services on triple-net leases. Closing is expected in the fourth quarter of 2026.

Participants & roles

  • Blackstone Digital Infrastructure Trustlandlord

    Through subsidiaries, to acquire a 75.1% controlling interest and act as managing member of the joint ventures that own and lease the campuses.

    Source
  • Amazontenant

    Amazon Data Services contributes the campuses, retains a 24.9% interest through affiliates and leases 100% of the properties; Amazon.com, Inc. guarantees the lease payments.

    Source

Terms as stated

Weighted average initial lease term 12 years (fully extended 32 years), 2.75% annual escalator; closing expected in Q4 2026, outside date Dec. 31, 2026 unless extended.

Announced

Figures as stated

contract value usdcommitted
$5B

As stated by Blackstone Digital Infrastructure Trust ·

'aggregate gross value of $5.0 billion, reflecting an initial capitalization rate of 7.0%' for both campuses; subject to closing conditions. A transaction valuation, not capex.

Blackstone Digital Infrastructure Trust (SEC Form 8-K) source

Status history

  1. Signed

    BXDC subsidiaries entered a contribution agreement with Amazon Data Services affiliates on Nov. 11, 2026; announced Nov. 16.